|
Home > Awards > King's Cross Redevelopment Programme: Package 4
King's Cross Redevelopment
Programme: Package 4 |

86.7%
|
Interim Client & Outline Design Award
Project Team:
Client: Network
Rail and
Argent
Design: Waterman
Civils Limited, Waterman
Building Services, Pascall
& Watson
Construction: Taylor
Woodrow
Sub-contractors:
Morrisroe (Concrete and steel),
McGee (Groundworks), Cementation (Piling)
The Project
King’s Cross station is at the heart of the busiest
transport interchange in the country with over 47 million
people using the station every year. This figure is
expected to rise by a further 10 million within a decade
due to increased tourism and major events taking place
in London, such as the 2012 Olympics.
King’s Cross Package 4 is part of a wider development
of the area and has a total value of £28.3m. The
project consists of the construction of a 10-metre-deep
basement with access ramp to house a plant room and
service yard which will facilitate the main station.
The new service yard will accommodate services such
as waste disposal and deliveries that are currently
undertaken in the operating station.
|
Aerial
photograph of the site between St Pancras
Station (bottom left) and King’s Cross
Station |
|
The works required:
- Over 370 piles as part of
a ‘top down’ construction method
- Approximately 43,000m³
of soil to be excavated
- 10,000m3 of reinforced concrete
and
- 1,850 tonnes of reinforcement
to be constructed.
|
Diagrammatic
representation of Package 4 showing extent
of contiguous piling and part top down approach
to construction |
|
Groundwater/water resources
Early consultation was made with the Environmental
Agency to ensure that the proposed piling technique
did not affect the underlying Major Chalk Aquifer. Ongoing
consultation was also made with Thames Water to ensure
that the project obtained the consent to discharge groundwater
from the site.
Archaeology
Heritage/Archaeology specialists were consulted early
in the development process to ensure that potential
archaeological features (such as the Milk Dock Wall)
were not affected by works
Community
Led by a dedicated Community Liaison Officer, the
project team, has
- set up a series of fundraising events for local
charities
- developed partnerships with local community groups
and businesses and
- organised networking events for sub-contractors
to meet local recruitment and training agencies.
One such partnership is with the London Wildlife Trust
at the neighbouring Camley Street Natural Park. Fundraising
events have been undertaken to raise money for the Trust
to help them buy new boats to be used for maintenance
and community outreach programmes.
Contaminated Land
Historically, the site and immediate surrounding area
comprised railway lines, a railway goods yard, an engineering
works, a garage and a clothing factory. Gasworks also
have extended onto the northern part of the site at
one time. Various site investigations and a Phase I
desktop survey were carried out as part of the planning
and design process.
Waste
Due to the significant quantities of excavated material
and the high diversion from landfill targets set in
the early phases, a waste ‘broker’ was used
on the project. The use of this broker minimised the
amount of material that required disposal in a landfill
and increased the amount of material that could be reused
or recycled.
|
Photograph
of SSY basement taken with fish-eye lens
to capture the extent of the excavation |
|
Noise
Noise monitoring was undertaken early in the design
phases at seven identified receptors to establish baseline
conditions. A Section 61 consent is also in place with
the local authority.
Heritage - Suburban Train Shed
The majority of works run directly parallel with this
significant heritage feature so working methods had
to be altered to ensure the protection of this Grade
I listed Building.
|
‘Bottoming-out’
celebration with site, client and Taylor
Woodrow teams on the successful completion
of the basement excavation |
|
Key Contacts
Taylor Woodrow Project Manager: Richard Wall Morris,
07816 514932, richard.wall-morris@taylorwoodrow.com
Environmental Manager/CEEQUAL assessor: Dawn Watson,
07816 515568, dawn.watson@taylorwoodrow.com
Environment Team Leader - Technology Centre/CEEQUAL assessor:
Paul Sandall, 07816 514507, paul.sandall@taylorwoodrow.com
|