|
home > awards
Barrow Gurney
Reservoir |

92.3%
|
Whole Project Award
Project Team: Bristol
Water (client), Black
and Veatch (design), Costain
(construction)
The project
The objective of the project was to construct a 40mgl
four-chamber partially buried and covered concrete reservoir
with ancillary emergency pumping equipment. In addition,
a controlling flow-brake unit for emergency or maintenance
emptying was to be constructed, which would also serve
as stormwater retention to prevent flooding of an adjacent
stream, used to carry discharges.
The six-acre site was contained within the Barrow Gurney
treatment complex, just to the south of Bristol, on
a part-brownfield site that had been used for storage.
To maintain the integrity of supplies to around 250,000
properties to the north, south and east of Bristol,
connections were to be made to several existing and
one new 13-km pipeline (the Northern Relief Main, which
was assessed separately under CEEQUAL and received a
‘Good’ Award).
Environmental considerations
A mature hedgerow traversed the footprint of the reservoir
site, and environmental reports had indicated that this
was used as a bat corridor linking two woodland areas
on either side of the site. An innovative approach was
taken to relocate the hedgerow as it stood, rather than
replace it with a newly planted hedge that would require
several years to mature.
During the dormant winter period, the entire hedgerow
was relocated to a prepared trench at the edge of the
site. Spring was awaited eagerly to see if the hedge
would take. To the project team’s surprise and
delight, the whole hedge blossomed and put on vigorous
amounts of fresh growth. In fact, by late April three
bird’s nests were recorded within the hedgerow
with pairs of blackbirds, hedge sparrows and chaffinches
all raising young.
Three semi-mature oak trees that were in the footprint
area of the reservoir had to be felled. The timber was
then used to provide additional bat roosts and invertebrate
habitats along the edges of adjacent woodlands.
Protecting the environment
The site is bordered by a small stream that was to
be used to disperse discharge from rainwater displacement
from the reservoir and, in an emergency or for maintenance,
for dewatering of one or more of the reservoir chambers.
In order to protect downstream properties, a valve-controlled
flowbrake chamber that can retard the rate of discharge
and provide dechlorination of potable water was built
adjacent to the main structure. This ensures that no
damage can result to the environment or to third parties
below the structure.
Waste minimisation and biodiversity
All excavated material was retained on site and reused
for green roofing and landscape bunding that was planted
with trees, grasses and wildflowers to provide a haven
for insects and foraging areas for bats, birds and small
mammals. This gave huge savings on transport and disposal
costs and substantially reduced the carbon footprint
of the project.
Use of materials
During construction of the reservoir, reusable aluminium
and steel formwork was used in preference to wood. In
fact, the use of wood in the whole construction process
was minimal (mainly for fencing) and all timber products
used were from FSC-certified sources, a condition built
into contracts issued to sub-contractors.
|