|
home > awards
Parc Cybi |
94.6% |
Whole Project Award
Project Team: Welsh Assembly Government (client),
Atkins (project manager and designer), Austin-Smith:Lord
(designers), Jones
Bros (Ruthin) Ltd (contractor)
The Project
The Parc Cybi (formerly Ty Mawr, Holyhead) business
park development is located on the southern approach
to Holyhead, Anglesey, and represents a major strategic
development for Holyhead and for Anglesey as a whole.
CEEQUAL has been used as the tool to both promote and
assess the strong environmental quality and sustainability
of the project. The high score achieved reflects the
integrated approach taken by the client, design teams
and contractor, and the commitment of all parties to
sustainable development.
The infrastructure works, which have been assessed
using the Whole Project with Interim Award approach,
comprise the masterplanning for the landscaping of the
site and the installation of the drainage, lighting
and access roads (including a new road linking the A55
with Trearddur Bay - Kingsland Road). Key drivers have
been the significant archaeological and ecological features
within the site, and the particular character of the
area in terms of its landscape, vegetation and cultural
heritage.
Site character
The site is located in an Area of Outstanding Natural
Beauty (AONB) with a gently undulating topography. The
site includes areas of improved grassland, which have
been used as pasture for both sheep and cattle, interspersed
with a number of rock outcrops colonised by gorse and
small areas of wetland. Field boundaries are defined
by natural stone walls containing, in places, sections
of wind-sculpted hedgerow. Many of the stone walls follow
the alignments shown on the first edition OS plan for
the area, and consequently represent an aspect of the
cultural heritage of the site.
|
Masterplan showing
both the new development and the areas of
untouched green space |
|
Infrastructure Works
The infrastructure built as part of the first phase
of the site development to facilitate the development
of business units includes some 1,500m of new carriageway,
including earthworks and a bridge over the existing
lane of Lôn Trefignath, foul and surface water
drainage systems, and utility supplies.
The surface water drainage within the site has been
designed using SUDS techniques with the aim of maintaining
the existing hydrology of the site and prevent, as far
as reasonably practicable, any increased run-off and
pollution occurring beyond the site as a result of the
new development. Implementation of the SUDS system has
also enhanced the wetland habitats present within the
site.
The road specification was written so as to give the
maximum opportunity for re-use of material and to minimise
the amount of material removed from the site. This enabled
the contractor to construct the highway embankment and
lay the sub-base aggregate using site-won materials
with no earthworks material being removed from the site.
Archaeology
Holyhead and Anglesey have a long history of human
occupation. Archaeological remains known to exist within
the site include a standing stone, remains of Bronze
Age occupation and Iron Age/Romano-British settlement
activity. The extensive archaeological works conducted
on the site have sought to investigate and catalogue
these areas and communicate the findings to the public
where possible. Two open days have taken place at the
site for the public to view the archaeological findings
and understand the work in more detail. Further information
was provided through a dedicated website and online
'dig diary'.
|
Standing stone at
the north end of the site, and an aerial
photograph showing the extent of the 36ha
area cleared for archaeological investigation. |
|
Ecology
The Parc Cybi site is dominated by large areas of improved
pasture, interspersed with rock outcrops, covered by
gorse scrub and semi-improved acid grassland, and areas
of low-lying marshy grassland. Several areas of standing
water were present within these marshy areas, along
with a drainage ditch, which had become dominated by
reeds. Detailed ecological surveys conducted at initial
design stage identified the presence of badgers, water
voles, smooth and palmate newts and lizards. Mitigation
measures were consequently included in the infrastructure
design and the masterplan to reduce the potential impacts
on fauna within the site. Habitats identified as of
value for nature conservation were managed to meet sustainability
targets of zero net loss in biodiversity. Areas of higher
ecological value were not developed and measures employed
during construction to prevent any impacts on these
locations. Enhancements to wildlife habitats across
the site, including wetland areas, re-seeded grassland
and new or re-built dry-stone walls, resulted in a net
increase of >65% in the area of wildlife habitat
available compared to the original undeveloped site.
|
Dry stone walling
on the site, rebuilt by specialist stonemasons.
Over 3km of new and rebuilt walls provide
habitats for reptiles as well as retaining
the local character of the site. |
|
Landscaping and site layout
The characteristics of the site, along with the important
archaeological and ecological aspects, were key considerations
in the development of the masterplan and the siting
of access roads and building plots. The masterplan was
developed to ensure that:
- The development would fit within the east-west topographical
grain of the site. This creation of essentially linear
strands of development would enable the important
ecological aspects of the site (primarily the rocky
outcrops and high ground) and elements of the natural
landscape to be retained, as well as allowing views
into and through the site.
- The visual interrelationship between off-site and
on-site archaeological monuments was maintained.
- The existing dry-stone walls and associated hedgerow
were retained. The new spine road for the development
was located so as to be aligned with an existing wall
for example, which would encourage biodiversity and
give the site added character.
- The development would integrate with its immediate
context, encouraging views into the site and out of
the site from all aspects. Particular consideration
was given to the interface with the nearest adjacent
housing to the site, to ensure that the development
did not 'turn its back' on its neighbours. Non-vehicular
access through the site is to be promoted through
the incorporation of footpaths and a bridleway.
- The landscape treatment was in keeping with the
character of the Island of Anglesey. Exposure of the
site to the prevailing winds, for example, was a major
influence on planting selection and location. The
use of large trees for screening has been avoided,
as these would not survive the weather conditions
encountered.
- The old road of Lôn Trefignath, which runs
through the middle of the site was retained as a route
for non-vehicular access through the site, thereby
retaining this aspect of the rural character of the
site.
Construction
The integrated project team approach to the development
allowed ongoing refinement of the design throughout
the construction phase and maximised opportunities for
enhancing the environmental performance and sustainability
of the project. Examples of such opportunities included:
- Redesign to maximise use of on-site materials: Following
a review of the aggregate materials available on site,
the designs for the roadway, drainage and utilities
were re-evaluated by the project team, so as to maximise
the use of site-won material and minimise the need
to import materials. In total, more than 12,000 lorry
movements (and 180,000+ lorry miles) were avoided,
resulting in significant reductions in energy usage,
road congestion and disturbance.
- Reducing energy requirements in operation and future
maintenance: By redesigning the street lighting, it
was possible to reduce the overall number of lights
required. As well as cutting the future energy needs
of the site and reducing light pollution, the removal
of wall-mounted lighting negated a requirement for
those walls to have a concrete core, thereby increasing
the area of reptile habitat available, and further
reducing material requirements for the site. Ongoing
maintenance requirements were reduced by changing
the specifications for the bridge parapet over Lôn
Trefignath from painted steel to aluminium, as well
as by returning the future building plots to grazing
until they are ready for development, thereby avoiding
the need for mowing. Cross ducts were installed under
the roadway to allow for the future installation of
a combined heat and power system.
- Selection of materials with high recycled content
where possible, such as the use of paving setts made
from secondary aggregates instead of granite setts.
- Use of alternative approaches in order to minimise
the temporary use of materials that would normally
be disposed of to landfill. Tree shelters made from
biodegradable material were used in place of plastic
ones, and exposed soil strips were used instead of
plastic reptile fencing. The combination of this intention
to minimise off-site disposals to landfill, together
with effective site inductions, removed the need for
7km of chestnut fencing, and 2.4km of plastic reptile
fencing.
|
Construction of the
reinforced earth bridge abutments - the
span of the bridge across Lôn Trefignath
was increased to avoid the need to divert
a medium-pressure gas main. |
|
|