|
Home > Awards > A58 Blackbrook Diversion Scheme
A58 Blackbrook
Diversion Scheme
Winner of a CEEQUAL Outstanding Achievement Award 2011 for Ecology & Biodiversity |
86.5% |
Whole Project Award
Project Team:
Client: St
Helens Council
Designer: Gifford
Contractor: Birse
Civils
The Project
|
Award presentation for
A58 Blackbrook Diversion Scheme |
|
The A58 Blackbrook Diversion has successfully removed
20,000 vehicles a day from the village of St Helens.
The new road, a single-carriageway bypass involving
1.6 km of new road and a new roundabout, runs close
to Clipsley Brook and passes over Black Brook, which
has been diverted through a new culvert.
The scheme design included the following:
- providing
mitigation for sensitive habitats and species impacted
by the scheme
- creating additional conservation
areas
- integrating the landscape
and ecological principles outlined within the Stanley
Bank Environmental Planning Framework
- provision of a Sustainable
Drainage System incorporating new ponds and wetlands
to alleviate flooding
- landscaped bunds and acoustic
fencing
Sustainability embedded from the outset
The bypass runs through one of the most environmentally
important areas in St Helens, with a local nature reserve,
Stanley Bank Site of Scientific Interest (SSSI), and
Semi-Natural Ancient Woodland sitting alongside industrial
remnants, such as an iron-slitting mill. A proactive
approach to sustainability ensured environmental issues
were embedded into the centre of the project rather
than as a statutory bolt-on.
The team benefitted from the expertise of the Environment
Agency, local stakeholder groups and regional advisory
groups. The project team was therefore able to draw
on the local and technical knowledge of a wide range
of individuals and organisations, ensuring that ideas
and innovation were integrated into the wider project.
Environmental and community benefits
The bypass:
- significantly reduced traffic
on West End Road, improving the environment and safety
- improved access to St Helens
for commercial traffic, assisting the economic regeneration
of the town
- included extensive landscaping,
sympathetic to the character of the area, to enrich
the wildlife habitat of formerly intensively farmed
land
- allowed the creation of wetlands
and grassland, benefitting water voles and dragonflies,
whilst woodland and scrub planting provided nesting
space for a variety of birdlife
- improved access to Stanley
Bank area by providing new recreational footpaths
Sustainability in planning, procurement and design
A detailed Environmental Impact Assessment was conducted
by St Helens Council. After extensive planning consultation,
it was considered important that the scheme enhanced
and expanded the natural habitat and environment for
the benefit of the local community.
From the outset, St Helens were determined to achieve
“something special” in terms of environmental
sustainability. The use of Early Contractor Involvement
with Birse Civils and their designer, Gifford, enabled
St Helens Council to develop a strong commitment within
the team to delivering this from design through to construction.
Improved management processes
A meeting was held in the early stages of the project
to identify practices to manage or mitigate environmental
risks and add environmental value to the project. This
involved all stakeholders to capture everyone’s
aspirations for the project.
A number of environmental management processes were
introduced to ensure environmental issues remained at
the forefront. Central among these were the Construction
Environmental Management Plans (CEMP) and Site Waste
Management Plans (SWMP). The SWMP was developed using
guidance from the Department of Trade and Industry,
Envirowise and the Groundwork Trust and was implemented
on a voluntary basis by the project team to deliver
best practice.
Protection of wildlife, habitats and the local ecology
The team utilised specialist expertise to protect key
wildlife within the site:
- Prior to commencement, a survey
undertaken by the project team identified a population
of water voles near to the construction footprint.
A trained ecologist relocated the water voles until
construction work was completed.
- The Environmental Impact Assessment
identified the presence of bats roosting at the site
together with a number of environmental features supporting
this population. During construction, a survey was
undertaken by a bat ecologist of all habitat features
that could be affected. The long-term wellbeing of
the population was supported through habitat connectivity,
sensitive use of street lighting and the installation
of numerous bat boxes around the site.
- The local area was identified
as an important area for wintering birds and sensitive
timing of works such as scrub clearance was required
to avoid the bird nesting season.
Sustainable Drainage System (SUDS)
The implementation of a Sustainable Drainage System
was a main planning consideration, forming part of the
Stanley Bank Environmental Framework.
Designed to address the problems of traditional drainage
schemes, the attenuation ponds within the SUDS store
surface water, which is later dissipated through natural
means, i.e. solids can settle and water is filtered
back naturally into the substrata.
The development of the SUDS also improved biodiversity
by creating a natural habitat for water voles, dragonflies,
invertebrates and moths. The scheme made a major contribution
to the North Merseyside Biodiversity Action Plan.
Management of invasive weeds
A number of invasive weeds, such as Japanese Knotweed
and Himalayan Balsam, were identified during the Environmental
Impact Assessment. These were considered detrimental
to the indigenous flora and the integrity of the road.
A specialist subcontractor used a combination of excavation
and spraying to remove the weeds using a Knotweed Eradication
Strategy that followed the Environment Agency’s
Code of Practice.
No materials were taken off site, instead the materials
were relocated on site for treatment and to be developed
into a feature for the St. Helens Gateway on completion
of the treatment regime.
Energy efficiency
The project addressed energy efficiency in a number
of ways, including looking at the introduction of renewables
and energy efficiency for the lighting on the site.
A Mayflower Intelligent Management System (MIMS) was
implemented for more specific control of the lighting.
Improved efficiency was achieved through the following
measures:
- Lux capacity can be adjusted
to suit the requirements of the user, allowing lighting
to be dimmed late at night when traffic is minimal,
thus saving energy and reducing light pollution.
- MIMS can predict bulb failure,
which is important, as failing bulbs use more energy.
- Energy consumption can be
measured, allowing savings over traditional billing
methods.
- The
use of down-lighting along the road reduced disruption
to local bat roosts.
Waste and resource efficiency
An Envirowise Site Audit addressed exactly what waste
was being produced and its location, so it could be
reduced. The site audit helped to:
- identify what was being done
before the resource efficiency initiative was started
quantify the environmental and financial savings made.
- An informal target of ‘10%
recycled content by materials value’ was set
for the scheme. This target was exceeded with an impressive
76% total recycled achieved.
Biodiversity
An independent audit assessed how biodiversity issues
were considered during the planning process, how they
were undertaken during construction, the quality of
monitoring and management of the outcomes. By identifying
key assessment areas, the team was able to effectively
identify and embrace nationally recognised best practice.
Measuring performance
Environmental performance was measured on Blackbrook
to determine the success of innovation and management
processes. The scheme achieved the following:
- Impact on the environment,
measured by customer satisfaction, at 95%
- Customer satisfaction for
Impact on Biodiversity at 95%
- The habitat area created and
retained in the project is 47%
- Level
of recycled elements within the finished product,
measured at 76%
|