|
home > awards
Rugeley
Bypass Phase 2 |
88.8% |
Whole Project Award
Project Team: Client Staffordshire County Council (Client);
Birse Civils Ltd & Birse Rail Ltd (Contractor) Staffordshire
County Council (Designer)
The Project
|
Award presentation for
Rugeley Bypass Phase 2 |
|
Rugeley Bypass was conceived to divert traffic away
from the congested centre of the small town and contribute
to the regeneration of the area. The bypass plays a
significant role in the sustainable regeneration of
mid-Staffordshire. The closure of Lea Hall Colliery
led to many job losses, leaving the area in need of
investment.
The scheme involved 2.2km of new bypass with footways
and a cycle lane, on a raised embankment through the
River Trent flood plain. The scheme has five major structures:
- two bridges over the River
Trent
- one bridge over the Trent
and Mersey Canal
- two under-rail bridges
The contract was awarded on an Early Contractor Involvement
(ECI) basis and sustainability was a priority from the
outset. Before construction started, the team held a
workshop to focus on all elements of sustainability
and determine key aims for the scheme. Individual specialists
were invited to contribute with their areas of expertise.
Other workshops included partnering, risk management
and value engineering,
Creating jobs through sustainable transport links
The new bypass connects the £10-million Towers
Business Park directly to the national highway network,
allowing it to achieve its true potential as a job creation
centre. Almost all the plots on Towers Business Park
have now been let. Economic experts expect the bypass
to create up to an extra 2,000 jobs. As a direct result
of improved transport links JCB have invested in their
Rugeley factory.
Recycling and sustainable materials: 97% fill materials
sourced locally
Working as an integrated team Staffordshire County
Council and Birse Civils have carried out the following
recycling:
- Using lime stabilisation to
treat existing embankment fill in place of imported
quarry materials
- 50,000m3 general fill has
been excavated from an adjacent local source and the
surplus 12,000 m3 of alluvial material excavated from
site has been back-hauled and placed in a borrow pit
- The surfacing base material
contained 75% recycled materials including road planings
for the aggregate and PFA for the binder
- Recycled hardcore has been
used for all temporary haul roads; upon completion
the roads have been removed and the hardcore recycled
again
- Over 4,000m3 of structural
concrete and non-structural concrete contains a recycled
alternative to cement
- By value 82% of the materials
used on the Rugeley project have been recycled or
contain recycled elements.
The team proactively used a Site Waste Management Plan
as a tool to manage waste issues. This was developed
from the DTI's voluntary code of practice in advance
of its introduction in April 2008.
Ecology: sustainable habitats to promote biodiversity
The new road crosses a Site of Biological Interest
(SBI), which is a wetland area known locally as Rugeley
Fen. During the planning stages of the scheme, several
environmental surveys identified protected species,
including:
- badgers
- otters
- crayfish
- bats
- nesting birds
The team have not only introduced mitigation measures
but have actively enhanced the ecology and biodiversity
of the project through:
- planting 5.1km of new hedgerows
to replace the 0.8km removed for construction
- creating mammal tunnels through
the embankment
- creating new foraging and
shelter habitats
- using wild-flower seed mix
in some areas to promote diverse insect life
- otter ledges on the river
bridges
Sustainable solutions to prevent flooding
Located close to the River Trent, Rugeley has suffered
severe flooding as recently as 2000. Building the new
road had to take careful consideration of this. A flood
compensation area was included in the works to create
a zero balance in material. The finished capacity of
the flood plain is equivalent to that prior to the bypass.
To mitigate concerns that the new road would act as
a drain for the Rugeley Fen wetland area, the excavations
and embankment were 'tanked' to keep groundwater on
the Fen. This was done using a bentonite geotextile
layer and has successfully maintained the groundwater
levels on Rugeley Fen.
Improving the local community
Extensive consultation and liaison was carried out
through the entire duration of the project from planning
to construction. During construction, the team used
the Considerate Constructors Scheme Framework to manage
the public interface and deliver community projects.
The overall sustainability of Rugeley and quality of
life for its residents will be enhanced through:
- improved road safety with a reduction of approximately
300 casualties over the next 30 years
- facilitation of improved public transport and aligned
bus and train timetables
- diversion of traffic onto the bypass has reduced
noise levels and improved air quality for residents
- improved cycleways and pedestrian routes linking
residential areas and creating the spine for cycling
and walking networks in Rugeley
2,000 local people attended a fun day to celebrate
Rugeley Bypass opening
|