|
home > awards
M40 Junction 15
(Longbridge) Bypass |
85.9% |
Interim Client and Design Award
Project Team: Highways Agency (Client); Morrison Construction
(Contractor); Hyder Consulting (Designer)
The Project
The team designed a dual carriageway bypass of the
M40 Junction 15, allowing vehicles travelling on the
A46 to avoid this busy junction. The bypass will be
routed to the west of the junction and connected to
the existing A46, north and south of the motorway. The
existing M40 Junction 15 roundabout will be widened
to four lanes, the approaches to the roundabout will
be improved, and new traffic lights installed. The signing,
road markings, road lighting and road pavement will
be updated to improve safety and driver understanding.
A new 4-span bridge will be built to take the new dual
carriageway over the M40 motorway.
The southern connection between the new dual carriageway
and the A46 Stratford road will be a roundabout, which
will also provide access to the B4463 and M40 Junction
15. The roundabout will include underpasses to allow
the safe movement of farm vehicles and pedestrians,
cyclists and equestrians under the A46.
Ecology and Biodiversity
A large maternity bat roost was discovered in two ash
trees adjacent to the M40 scheme footprint. The roost
was one of only two large Noctule roosts known to English
Nature (now Natural England), the other being near Cambridge.
Due to the importance of the roost and the risk of disturbance
from the scheme during both construction and operation,
English Nature advised that they would formally object
at Public Inquiry if the scheme were to go ahead unchanged.
Following an extensive optioneering exercise, a revised
scheme further east towards the village of Sherbourne
was developed, which moved the proposed A46 bypass approximately
200m away from the roost.
In addition to the work on bats, ecological surveys
were carried out in relation to flora, amphibians and
other mammals. Advance works include plans for translocation
of reptiles from existing highway verges to identified
receptor sites nearby. The scheme design includes mammal
mitigation to allow badgers and otters to cross the
scheme via special underpasses and ledges within culverts.
Archaeology
The scheme is situated on terraces of the River Avon
and these terraces have proved rich in archaeology in
the past. A number of discoveries have been made in
this general area, including various crop marks and
henge sites (now Scheduled Ancient Monuments). In order
to address concerns from Warwickshire County Council
that further significant archaeological remains might
be disturbed by the scheme, a comprehensive scheme of
geophysical surveys and trial trenching was carried
out, both on land required for the scheme itself and
proposed borrow pits. To date, however, nothing significant
has been found.
Sustainable design
Sustainable drainage principles were adopted in the
drainage system designs. Whereas drainage current flows
directly into watercourses within the scheme area, run-off
from the proposed scheme will be fed through a system
of five storm-water wetlands. This will not only provide
attenuation and reduce peak flows, but will also help
to treat run-off and remove contamination. Although
not their primary purpose, the ponds will also provide
improved habitat diversity and feeding opportunities
for other species.
Borrow pits have been identified adjacent to the scheme
to provide the significant volume of fill material needed
(in the order of 700,000m3). Planning permission for
the borrow pits was obtained via a separate planning
application. By obtaining the material locally, thousand
of lorry movements will be avoided, bringing substantial
benefits to local residents by minimising impacts on
local air quality, noise and disruption during construction.
Environmental and Community Liaison
The scheme has been developed in close co-operation
with various statutory consultees including Natural
England, the Environment Agency and the local authorities,
Warwickshire County Council and Warwick District Council.
Summary
An 'Excellent' CEEQUAL Interim Award has been achieved
by careful consideration of environmental issues from
the outset, as described above. With input from the
Morrison team, the scheme has been designed to minimise
environmental impacts and ensure that design of the
final scheme is sustainable. The development of a Construction
Environment Management Plan shows a commitment to long-term
environmental management during construction and operation.
|