|
home > awards
A30 Bodmin to
Indian Queens Improvement |
86.2% |
Project Team: Highways Agency (client), Mouchel (client
representative), Alfred McAlpine (main contractor),
Scott Wilson (Designer), RPS (client environmental advisor)
Scheme Details
Cost of Scheme: £93million. Construction cost:
£60million
Length of new dual carriageway: 11.5km (7 miles) also
6.5km of side roads.
Work Started: July 4th 2005. Mainline Completion: July
11th 2007
New Structures: Three over-bridges / four underpasses
/ two grade separated junctions.
Earthworks: 970,000 cubic metres of excavation and
700,000 tonnes of imported china clay waste of which
230,000 tonnes were supplied as surfacing materials
Background
Schemes to improve the A30 between Bodmin and Indian
Queens have been examined since the 1970s. Large seasonal
variations in tourist traffic resulted in severe congestion,
affecting communities and businesses, and the route
of the old A30 bisected a nationally important piece
of Moorland designated a Special Area of Conservation
(SAC) and a Site of Special Scientific Interest (SSSI).
An obstacle to heavy goods vehicles, the low ‘Iron
Bridge’ rail crossing, forced lengthy diversions
along minor roads and severe delays occurred regularly
across the region resulting from collisions with the
structure, while low visibility at busy side roads caused
frequent accidents.
Traffic volumes are forecast to increase from 25,000
to 37,000 vehicles per day by 2022, with particular
problems during the summer months. As most of the A30
from Exeter is now built to dual carriageway standards,
the single carriageway between Bodmin and Indian Queens
presented a major bottleneck.
Benefits of Early Contractor Involvement (ECI)
The A30 Bodmin to Indian Queens scheme was one of the
first to be procured on an ECI basis. Although ECI is
now the norm, in 2002 it was considered a dramatic step,
showing the Highways Agency’s commitment to improving
value through effective partnering and proactive procurement.
The ECI process has allowed the project team to develop
and grow in a trusting and mutually respectful environment.
Continuity of delivery team staff has resulted in a
dispute-free scheme, where all members have genuinely
worked together with a common goal and common objectives.
Specialist supply chain partners were brought to the
team early. Proactive partnering with the supply chain
resulted in no disputes and early settlement of final
accounts.
Central Cornwall is home to a large china clay quarrying
industry, which produces granite-based sand and gravel
as a waste product. 98% of the imported stone was sourced
using this waste as secondary aggregate. Bardon Contracting,
Bardon Aggregates and Needham & Cullen (all part
of the Aggregate Industries Group) used their joint
expertise to maximise the use of china clay waste.
Construction Design Rationale
The key objective was to build the new road with minimum
impact on traffic flows through and around the scheme.
The construction plan allowed for the building of a
permanent diversion at Mount Pleasant and the early
opening of the two junctions at Innis and Victoria.
As part of the Mount Pleasant section, an underpass
connected the existing Roche Lane junction with the
new diversion. This allowed earth-moving traffic to
pass from one end of the scheme to the other without
impacting on users of the existing A30.
Initially, at the Innis Downs junction, the preferred
route indicated two bridges with the intersection overlaying
the existing roundabout. The project team developed
the chosen solution to build a top-down bridge at ground
level in the middle of the existing roundabout and,
subsequently, the two dumbbells, with minimal disruption
to the travelling public.
At the Victoria Interchange, the preferred route crossed
the existing line in the proximity of a required interchange.
To minimise disruption, the interchange location was
moved to allow full off-line construction, with disruption
only experienced during night-time tie-in work.
At the Indian Queens tie-in, the alignment was designed
to allow part-construction of the widened embankment
and the construction of a temporary alignment to facilitate
full construction with little impact on the travelling
public.
Heritage
Site clearance was completed under expert supervision,
as was the archaeological investigation, where, on land
near the hamlet of Belowda and at Deep Tye Farm, evidence
of human occupation of Romano-British and Bronze Age
origin was found.
The discoveries included the remains of a late Neolithic
(3000–2000 BC) henge, found during archaeological
investigations near Deep Tye Farm, 1km to the south
of Castle-an-Dinas hill fort.
The Deep Tye Farm Henge is believed to be the first
example of this type of circle-henge to be found in
Devon and Cornwall.
The layout, of a particularly rare form, consists of
an arc of pits forming a segmented ditch, 10m in diameter,
and an inner arc of 10 postholes, with a large gap facing
due south. Such monuments were built by the early farming
communities of Britain during the Neolithic period.
Near Belowda, excavations revealed remains of an Iron
Age round house, possibly used as a temporary shelter
by ‘tinners’ working the moor.
These structures have been fully excavated with the
finds undergoing laboratory analysis prior to publication
of the full report. To disperse the experience gained
on this scheme, a booklet has been produced detailing
the ecological and archaeological aspects of the pre-road
mitigation work.
Environmental Mitigation
Goss Moor is a Special Area of Conservation (SAC) and
in some areas the moor has SSSI status. The site was
previously bisected by the A30 trunk road. The improvement
reroutes the road to the north of the SAC to an area
of low-grade agricultural land.
Working in Partnership with Natural England, as part
of the European-funded LIFE Project, we were able to
enhance the area of the old trunk road route to provide
a natural amenity space for the public and allow the
moor to regenerate.
The route corridor encompasses the springs and headwaters
of two highly important and designated rivers and is
a vitally important area for fauna and flora.
Thirty hectares of arable land adjoining the road and
moor were purchased as mitigation land and passed to
Natural England for recreation of moorland. This is
equivalent to 30 times the amount of land taken that
had an ecological designation. This land provides a
valuable habitat and a sizeable extension to the moor.
Individual species mitigation
Reptiles
- Survey and capture of 361
Adders, Grass Snakes and Common Lizards and release
into mitigation land
- Use of reptile fencing to
prevent re-entrance of translocated reptiles
- Construction of 7 hibernacula
within 30 hectares of mitigation land.
Butterflies
The scheme has been used as a case study for butterfly
mitigation in the English
Nature/Highways Agency Butterfly Handbook.
Otters and Badgers
Installation of 13 crossings on established migration
paths.
Dormice
- Thorough search prior to removal
of vegetation under licence
- Habitat creation through establishment
of over 6.5km of planted Cornish hedge providing habitat
linkage
- Installation
of Dormouse bridges in key locations.
The landscape mitigation strategy included:
- Preservation and reuse of
moorland soils
- Collection of local provenance
seed from areas adjacent to the scheme
- Inclusion of large swathes
of wildflower grassland within the scheme
- Development of a new boundary
fencing system with a lower visual impact
- Functional mitigation through
landscape features, including landform and planting
to reflect and enhance the existing landscape character
- Expanding the diversity of
existing habitats within the highway boundary
- Woodland / shrub planting
to provide visual screening to built elements and
sensitive visual receptors, including local residences,
and to mitigate for loss of woodland areas
- Regrading of extensive areas
adjacent to junctions to be returned to agricultural
use
- Use of seed mixes to reflect
existing landscape character, changes in soil type
and to provide a range of ecological habitats.
Cornish Hedging:
Cornish hedges were created to maintain the visual
integrity of the field system, in addition to providing
screening and noise attenuation.
A Cornish hedge is a stone-faced earth bank with planting
in the top and has been used as a field boundary since
the Neolithic Age. Over 7.5km of new Cornish hedge were
constructed as part of the scheme, knitting together
the landscape and ensuring continuity with existing
boundaries.
They provide invaluable habitat for a plethora of species
including the endangered Dormouse. The hedges were planted
using traditional species offering food and shelter
for wildlife, and their linear nature provides excellent
connectivity, linking isolated habitat and increasing
biodiversity. All the hedges were hand-built, helping
to maintain important heritage skills, with all the
stone being sourced from neighbouring quarries.
Downgrading Works
After the Scheme was completed, the old A30 was downgraded
and, where it crosses the Goss Moor, facilities provided
for walking, cycling and an equestrian route, as part
of a network of multi-use trails being established by
Natural England around the wider reserve. This will
effectively rejoin the two parts of the moor, providing
benefits for a number of species, in particular the
Marsh Fritillary butterfly, by increasing the quality
and quantity of breeding habitat and enabling colonisation
of sites by reducing isolation.
Sustainability
Over 98% of the imported stone used for the entire
works was sourced from the china clay industry, thereby
utilising a waste product available in abundance in
the vicinity of the site. With the china clay industry
in decline, the use of this waste material provided
an economic benefit to the local community in difficult
times.
A mobile coating plant for the surfacing was established
at the source of the secondary aggregate, further minimising
transport impacts through local villages.
Existing roads that were no longer required have been
planed and the chippings reused for access tracks.
All vegetation and roots cleared were chipped and reused
as mulch.
The scheme was carefully designed to have an exact
balance of cut-and-fill, negating the need to import
or export material.
Community
Early consultation with Natural England, Cornwall County
Council, the Environment Agency, local Parish Councils
and various community groups continued through the construction
process, ensuring close and successful public involvement
through a dedicated liaison process. This involved regular
presentations to schools, professional bodies, educational,
local interest and environmental groups and operating
a continual series of site tours as work progressed.
Regular support initiatives for local charities culminated
in a sponsored walk through the scheme prior to road
opening, which attracted a county-wide involvement,
raising over £14,000 for local charities.
As part of the archaeological site investigation, groups
of students were invited to become actively engaged
in excavation works.
The success of this scheme was built on robust and
continuous consultation. The design and construction
adopted a holistic approach in trying to understand
the many varied aspects, constraints and opportunities
in order to deliver effective environmental mitigation
that will provide lasting benefits to the environment,
economy and people of Cornwall.
Roads Minister Stephen Ladyman said: "Pioneering
work on the A30 Bodmin to Indian Queens scheme shows
how we can reduce the environmental impact of a major
road project. It is an excellent example of finding
a local solution which benefits local people, the local
economy, the landscape and the environment.
|