|
home > awards
Hademore Level
Crossing |
|
Construction-Only Award
Contractor: Norwest Holst Ltd
The Project
The £8 million project forms part of the Trent
Valley Four Tracking (TV4T) scheme, which encompasses
a 12-mile stretch of the West Coast Mainline between
Tamworth and Handsacre. Norwest Holst was awarded the
Hademore Level Crossing contract in early 2006, which
involved the construction of a new bridge to replace
the level crossing, 1km of rail widening and five other
reinforced concrete structures. Overbridge 90AA (OB90AA)
replaces the level crossing and comprises a single-span
portal structure with 600m of approach road on 8-m-high
embankments. Approximately 80,000m3 of material was
required for the embankment construction. The works
interfaced with residential and commercial properties
as well as agricultural land, the Birmingham and Fazeley
Canal and a brook.
|
Aerial view of OB90AA and the associated
embankments
|
|
Cultural Heritage
To construct the approach road to OB90AA, it was necessary
to dismantle and relocate a pair of Grade II Listed
gate piers, which flanked the drive to Fisherwick Hall
(now demolished). These gate piers were not only of
cultural heritage value, they also offered nesting habitat
for the Tree Sparrow (Passer montanus).
The planning consent required the piers to be dismantled
stone by stone, numbered and dressed, and then moved
to a secure storage area prior to re-erection. However,
before commencing the dismantling process it was necessary
to carefully remove the vegetation covering the piers
and wrap them in debris netting. This measure was adopted
in order to prevent tree sparrows from nesting in the
piers, as they had been known to do in the past, thus
ensuring there were no delays to the proposed works
later in the year.
However, the netting of the gate piers meant that
potential nesting habitat had been removed, which could
have adversely affected the Tree Sparrow population
in the area. It was therefore decided to erect nesting
boxes in close proximity to the gate piers, offering
alternative nesting opportunities for these birds.
In accordance with the Planning Consent and the Specification
for an Archaeological Building Recording as issued by
Staffordshire County Council, the dismantling process
was fully documented and photographically recorded by
The Linford Group Ltd (specialist stone masons) in partnership
with Norwest Holst.
The gate piers now form a focal point on Fisherwick
village green, much to the satisfaction of the Parish
Council and the local residents. The efforts of the
project team ensured that a 100% score was achieved
for this section within the CEEQUAL assessment.
|
Gate piers re-erected on Fisherwick
village green
|
|
Sustainability and Material Reuse
Since the works associated with the TV4T scheme were
being carried out by a number of different contractors
simultaneously, the demand for fill material import
was high. Even though a number of quarries exist in
the region for the import of material, Norwest Holst
decided that an embankment design had to be produced
that mitigated the risk of supplier shortages. It was
essential to give the client maximum assurance that
the critical date of Christmas 2006 for the opening
of the bridge would be achieved. The consequences of
not achieving the date would have led to a significant
delay to the TV4T scheme.
On this basis it was decided that Pulverised Fuel
Ash (PFA) would be a suitable alternative to quarried
material and could be provided exclusively by Rugeley
Power Station. Furthermore, detailed research showed
that a heavy-duty geotextile could be used, instead
of oversize stone, to prevent capillary action at the
base of the embankment.
The substitution of quarried material for PFA and
the use of a geotextile prevented exploitation of natural
resources and thus minimised the environmental impact
of the project on the local area. Using PFA as general
fill puts the material back into the supply chain and
effectively constitutes the reuse of a waste product.
The lighter bulk density of PFA in comparison to stone
helped to remove haulage vehicles from the public highway
and resulted in a subsequent reduction in carbon emissions
during the delivery and placement process.
Class 2 clay used to retain the PFA during fill operations
was sourced from other projects on TV4T that had a surplus
of material. This would otherwise have been taken to
a waste disposal facility, therefore Norwest Holst ensured
a ‘Win-Win’ scenario with the client –
import and disposal costs were reduced by diverting
material from landfill.
The use of PFA as well as suitable ‘cut’
material from within the TV4T scheme envelope ensured
that 57% of the materials used as bulk-fill were reclaimed
and therefore reused. This, amongst other initiatives,
ensured a percentage score of nearly 90% in the Material
Use section of the CEEQUAL assessment.
Community Relations
Throughout the project, local stakeholders were informed
of construction activities via regular newsletters and
were also invited to attend open evenings in which they
could raise concerns over the programme of works. The
project was also registered under the Considerate Constructors
scheme and gained positive feedback during the audit
process.
In partnership with Network Rail and the British Trust
for Conservation Volunteers (BTCV), Norwest Holst donated
materials, labour and expertise for the improvement
of a wildlife garden at Moorgate Primary School, Tamworth.
The aim of the project was to make the garden more accessible
for the school children so that they could spend more
time studying amphibian and reptile species as well
as invertebrates.
The flexible approach of the site team ensured that
high percentage scores were achieved in both the Nuisance
to Neighbours and Community Relations sections of the
assessment.
Summary
The CEEQUAL assessment process enabled the site team
to constantly monitor environmental performance of the
project and identify weak areas where improvements could
be made. Norwest Holst is proud to have been the only
contractor that registered a project for CEEQUAL assessment
within the TV4T scheme and the ‘Very Good’
rating is testament to the fact that contractors can
make a difference regardless of client or designer involvement.
|