|
home > awards
Thames Water
Ring Main Tunnel Extensions – AMP4 London
Resilience Programme: 6DCF New River Head to
Stoke Newington |
87.2% |
Interim Client and Outline Design Award
Project Team: Thames Water Utilities Ltd (client) London
Clean Water Network (LCWN) and Mott MacDonald (designer)
|
New site for the London
Wildlife
Trust Environmental Classroom |
|
The Thames Water Ring Main (TWRM) northern extension
from New River Head to Stoke Newington is one of the
two TWRM tunnel extensions within the AMP4 London Resilience
Programme. The southern extension project is 4DCF Brixton
to Honor Oak.
During the early stages of the project, a decision
was taken to register both projects for the CEEQUAL
award scheme to ensure the highest standards of environmental
good practice and design were achieved. The CEEQUAL
award is divided into two stages representing the key
project milestones, namely:
- Stage 1: Interim Award Stage
for satisfactory completion of planning and the outline
design phase.
- Stage 2: Whole Project Award
Stage for satisfactory completion of the construction
phase.
Following the successful completion of the interim
award by the 4DCF Brixton to Honor Oak project, the
6DCF New River Head to Stoke Newington project has also
completed the interim award. The 6DCF project was able
to identify and pursue even more opportunities in developing
environmental excellence during planning and design
stage.
|
Widened Access Road
and Provision
of Segregated Pedestrian Foot Path |
|
6DCF New River Head to Stoke Newington
The northern tunnel extension from New River Head to
Stoke Newington comprises a 2.5m internal diameter tunnel,
driven 4.5km from a new 48-m-deep shaft at the Stoke
Newington site to a new reception shaft at the New River
Head site. The tunnel will be constructed using precast
concrete segments and an earth pressure balance tunnel
boring machine. The Stoke Newington site is partly located
within a TWRM operational site and partly within Stoke
Newington West Reservoir site, owned by LB Hackney.
The Stoke Newington reservoir site is located on Metropolitan
Open Land (MOL) and is classified as a Conservation
Area. The site is a former water treatment works; the
old pump house (The Castle Climbing Centre) and its
environs, which date from the late 1800s, are classified
as grade II listed buildings. The site shares a common
access road with the West Reservoir Sports Centre, the
listed Castle Climbing Centre and a children’s
play centre. The New River Head site is located entirely
within an existing operational site, which is bounded
by residential houses and a school.
During the early stages of the project, an EIA Screening
Opinion Report was prepared, which concluded that the
project would not lead to any significant environmental
impacts and therefore the main tunnelling works should
proceed as Permitted Development. In order to make the
site suitable for construction traffic, it was necessary
to obtain planning permissions for access widening works.
Works undertaken during the planning and outline design
phase can significantly influence environmental impacts
during the construction phase. By highlighting key environmental
issues early and incorporating appropriate measures
into the outline design, a better overall environmental
performance will result.
|
West Reservoir Sports
Centre Sailing Club |
|
Key actions undertaken by the Client-Design team during
Interim Award stage included:
- Reducing construction impact
by careful consideration of locations for the tunnel
drive and reception shaft site. The outline design
removed the need to construct an intermediate access
shaft.
- An Environmental Management
Plan (EMP) was prepared, including an environmental
risk register, identifying key risks and mitigation
measures to be addressed by Thames Water and the contractor.
- A Tender Assessment Scoring
method was used, which gave consideration to the contractor’s
environmental track record.
- Environmental screening surveys
were carried out to identify likely environmental
impacts (e.g. traffic, noise, groundwater, archaeology
and habitat surveys).
- A Project Communication Plan
for liaising with all key stakeholders was prepared.
The key stakeholders comprised local authorities,
residents and users of the sports centre (sailing
club), climbing centre and children’s play centre.
Drop-in sessions were held at the main shaft site,
the local church and the Islington Business Design
Centre, where local residents and businesses were
invited to hear about the project and raise any concerns,
which were fed back to the project team.
- Landscaping and general access
improvements to Stoke Newington site. The landscaping
proposals were designed to complement the existing
site and improve pedestrian access to the sports centre
and New River Path.
Provision of a new wildlife area and environmental
classroom facilities for the London Wildlife Trust
at the Stoke Newington East Reservoir site.
- Pre-construction enabling
works were designed to improve access to the Stoke
Newington site. Upgrades included provision of a new
pedestrian walkway and guardrail, widening of entrance
gates, removal of undesignated parking at the site
entrance and between the trees with Tree Protection
Orders, and provision of designated car parking within
the sports centre.
|
Grade II Listed Castle
Climbing Centre |
|
Future Works – Construction Phase
Both 4DCF and 6DCF projects have been procured as Design
& Build contracts, using the Engineering Construction
Contract (ECC). The appointed tunnelling contractors
are required to develop the detailed design and carry
out the construction works. Construction has the potential
to create the largest environmental impact. Typically,
the key environmental issues during construction include:
- construction traffic nuisance
to local residents
- compliance with environmental
legislations (Section 61 and EA approvals)
- detailed design of the tunnel-lining
system
- recycling and/or disposal
of tunnel arisings, e.g. via other project sites or
aggregate/gravel pits.
- non-contamination of Source
Protection Zones (SPZ)
With the first part of the journey complete, London
Clean Water Network remain committed to working together
with the Design & Build contractor to ensure the
highest standards of environmental excellence are achieved.
|