|
home > awards
Rushall Embankment
Works |
|
Project Team: Morrison Construction/British Waterways
Omnibus Partnership. Client: British Waterways (West
Midlands Business Unit)
Morrison Construction/British Waterways Omnibus Partnership
is currently involved in a seven-year framework contract
to undertake a backlog of mainly safety-related works
on the canal infrastructure network throughout England
and Wales.
The Rushall Canal was built in 1802 and subsequently
suffered from subsidence due to mining at the nearby
Walsall Wood colliery, an issue addressed in the past
by the building up of embankments. An inspection in
2000 confirmed that they were leaking and this, combined
with the low freeboard, led to the need for embankment
improvements.
The CEEQUAL award is in recognition of environmental
best practice demonstrated on the Omnibus’s £2.35m
contract to stabilise the embankment of, and refurbish
two bridges over, the Daw End Branch of the Rushall
Canal near to Brownhills, West Midlands.
The works were located on the Daw End Branch of the
Rushall Canal between Aldridge Wharf Bridge at the southern
extent and to a point approximately 1 km beyond Anchor
Bridge on the northern extent and took place from March
2003 to May 2004.
The scope of works included:
- 5.3 km of new Breedon gravel towpath between Aldridge
Wharf Bridge and a point 1km to the north of Anchor
Bridge.
- Freeboard raising to 3 km of towpath side brick
wash wall.
- Freeboard raising to 300 m of offside, including
earth bund construction.
- Lowering of water level to allow inspection of the
wash wall and repair of the brickwork as necessary.
- 535 m of sheet piling within the line of the towpath
to stabilise the embankment.
- Strengthening to two brick retaining walls to the
north and south of Black Cock Bridge.
- Palisade fencing to the boundary with commercial
properties immediately to the north of Walsall Wood
Bridge.
- Installation of artificial reed margins to the front
of the offside sheet-piled wall between Lathams Bridge
and Hollanders Bridge.
- Northywood Bridge: grit-blast and repaint the existing
cast iron beams, replacement of existing wrought iron
jack arches, and refurbishment of the existing masonry
abutments and wing walls.
- Hollanders Bridge: fabrication of a new steel bridge
and refurbishment of the existing masonry abutments
and wing walls.
Key environmental considerations
Crayfish
An ecological survey in advance of the works revealed
42 white-clawed crayfish (a protected species) at 25
sites along the length of the Daw End Branch. They were
living in crevices created by dilapidated brickwork
that was to be replaced. To compensate for the loss
of habitat, the Omnibus incorporated 3- and 10-hole
perforated engineering bricks within the repaired canal
walls, together with short lengths of 40-60mm ducts
to accommodate the crayfish through the various stages
of their lifecycle.
Water voles
Water voles (another protected species) were evident
at seven locations along the offside canal bank. In
one area, the Omnibus needed to raise a 300-metre-length
of offside freeboard, work which was undertaken under
the close supervision of the team’s ecologist.
In another area the Omnibus had stabilised the bank
by sheet piling a length of the offside. The team then
improved water vole access and restored their natural
habitat through an innovative design incorporating prefabricated
reed margins that were fixed to the front of the sheet
piles just above water level. The margins took the form
of coir rolls containing a mix of hazel faggots and
soil, pre-planted with reeds and bound by wire mesh
matting.
Luronium natans
Lurionium natans (a protected plant species) was recorded
in the canal bed throughout the length of the Daw End
Branch. It was important, therefore, that the canal
bed silt was not disturbed during the course of the
works. To this end, piling was carried out from a rig
located on a pontoon in the canal. In addition, the
piling sub-contractor used a Movax vibro-impact piling
rig which uses vegetable-based oil and is quieter than
other rigs.
Scheduling & Training
The programme for the contract was governed by environmental
considerations. For instance:
- Work on offside freeboard
raising was deferred until September when the vole
population was at its most resilient.
- Vegetation clearance took
place between September and March to ensure it did
not coincide with the bird nesting season.
All site staff attended training courses led by a British
Waterways ecologist on the subjects of water voles and
crayfish.
|