|
home > awards
Snaresbrook Embankment
Stabilisation Project |
|
Project team: Metronet & Trans4m alliance, Cementation
Foundations Skanska)
Metronet Rail, in partnership with London Underground,
has been revitalising and upgrading two thirds of the
Tube. Part of this work involves strengthening and repairing
embankments, including one between Snaresbrook and South
Woodford stations located at the eastern end of the
Central line in Wanstead, East London.
The 100-year-old embankments along this stretch of
the Central line had deteriorated over the years and
the works were required to make them more stable. The
Project was undertaken by Metronet & Trans4m alliance,
with Cementation Foundations Skanska responsible for
the design and build contract. The CEEQUAL assessment
was conducted by Atkins.
The Snaresbrook Embankment Stabilisation Project was
conducted between the station bridge adjacent to Snaresbrook
Station and the subway at the end of Falcon Way. Works
were undertaken on the westbound embankment slope, which
is situated behind residential gardens off Sylvan Road,
and behind Trafalgar Place.
The site was identified as being in need of remedial
stabilisation works, which then took place between November
2004 and July 2005. Large parts of the upper portion
of the embankment showed bare areas, where loose ash-fill
surfaces were exposed and were actively ravelling down
the slope. This was causing crest stability problems
which, in turn, had undermined support to both the line-side
services and track. After an analysis of options, it
was concluded that the preferred solution would be to
construct a bored pile retaining structure along the
central areas of the embankment, with localised earthwork
berms at either end of the site
Environmental management
Metronet & Trans4m alliance is ISO 14001-registered
and all projects are carried out under the organisation’s
environmental management system. Hence, the principles
of effective environmental management were applied throughout
this project. The project team included a dedicated
environmental manager who provided ongoing support and
guidance to the project manager.
The project team showed its commitment to environmental
protection from the start, as other solutions that would
have involved extensive vegetation and tree removal
and a large amount of night-time working were rejected.
Ecology & landscaping
In order to conduct the essential stabilisation works,
it was necessary to remove some existing trees and vegetation
from the embankment. Ecology and landscaping were therefore
key environmental concerns for this project.
There was full consultation with the London Borough
of Redbridge, and comprehensive ecological surveys were
conducted to identify any protected flora and fauna.
Moreover, when nesting birds were discovered earlier
than anticipated in the initial survey, the whole project
was postponed by over six months. No other protected
species were identified on site. Nevertheless, a Metronet
& Trans4m alliance ecologist was involved to ensure
any potential issues could be managed effectively.
Wherever possible, existing trees were retained, with
both the construction scaffolding platforms and the
final structure re-designed to maximise tree retention.
A replanting programme is now underway to reduce the
visual impact of the repair works
Community liaison
The other key issue for this project was disruption
to local residents, which was managed with a high degree
of consideration and sensitivity by Metronet & Trans4m
alliance. The embankment backed onto some local residents’
gardens and properties, and hence some degree of disturbance
was unavoidable.
However, thanks to an extensive community relations
programme, which included press releases, letter drops
and face-to-face liaison, the project was received well
by the local community. A Metronet Rail Exhibition bus
visited the site to help promote awareness of the works
and to answer any queries from local residents and community
representatives, including the Mayor of Redbridge and
the MP for Ilford North.
With works completed, the project team was keen to
leave a positive impression and, by laying a new road
surface, clearing rubbish and erecting a new fence on
land which they had used as their site compound, they
were able to leave the area in a better condition than
before the works, much to the delight of local residents.
|