Environment
Agency and Babtie Brown & Root:
Littlestone Sea Defences |
85.1% |
The scheme was promoted by the Environment Agency with
funding from DEFRA. Design and supervision of the works
was carried out by Babtie Brown & Root, under their
framework contract with the Agency. The outline and
detail design works were fast tracked and completed
in
only 14 months including planning consent and public
consultation allowing construction started in June 2002.
Due to the scale of the scheme the works were split
in two phases, the first phase works consisting of the
rock works and the delivery of 82,000m3 of shingle.
Phase two was for the delivery of the remaining 158,000m3.
Construction was carried out by Westminster Dredging
/Van Oord ACZ Joint Venture. The Phase 1 shingle delivery
was carried out using the 'Volvox Scaldia' dredger which
discharged onto the beach via a 450m floating pipeline.
During the Phase 2 works the 'Volvox Scaldia' was joined
by the 'Sospan Dau' dredger which delivered onto the
beach via a method known as rainbowing, this is where
a jet of shingle is pumped onto the beach and placed
at low water by bulldozer.
A third Phase is planed for 2004 to raise the existing
concrete sea defences to a consistent level.
The scheme has been constructed to time and below target
cost.
|